Feedback:
To make a quality product, the target capability should always be tighter than the specifications.
Statistically, analysis of the capability of a new machine is as simple as using a slightly modified process capability index. However, when new machinery is involved, a number of other issues arise. When looking at new machinery it is not possible to examine all of the potential sources of variation, such as different operators, tool changes, fixtures, materials, etc. Other factors tend to work to increase the variability of new equipment. Kane (1989) lists several factors that work to affect the variability of new machines.
FACTORS INCREASING |
FACTORS REDUCING |
VARIABLITY |
VARABILITY |
AT MACHINE TRYOUT |
AT MACHINE TRYOUT |
Machine break-in |
Low production volume |
Special gauging |
Specially trained operators |
Nonstandard machine hookup |
Strict environmental controls |
(e.g., power, coolants) |
|
Usually, but not always, the combined affect of these factors is to decrease variability during the machine capability analysis. Statistically, the usual approach is to use stricter capability requirements for new equipment than for standard process capability analysis. In addition, the purchaser must use a modified approach to estimate the capability of the new machine prior to the purchase. Kane recommends the following approach to a capability analysis, which he calls a machine tryout.
Site — It is important to conduct the tryout at the machine builder’s site. This gives the opportunity to correct any deficiencies quickly. In many cases any lack of capability can be corrected by “fine-tuning” machine parameters. This process is time consuming and often requires a variety of engineering expertise. The required personnel and facilities are most accessible at the machine builder’s site.
Parts and material — As the process flow diagrams indicate, machines are often part of a sequential process of manufacturing a finished product. Machines that operate on various stages of semifinished products require parts or materials in the required semifinished stage of processing. For a new process all machinery is purchased at the same time, so it can be difficult to obtain the required parts. In many cases, these parts must be specially manufactured at a high cost. The quality of these special parts can be much better or worse than the normal production parts. To often, too few parts are available at a tryout to adequately evaluate a new machine.
Cycle time — The rate at which a machine produces parts is often related to the variability of the output. Thus, it is important to perform the tryout at the same cycle time used in normal production. This is a common oversight.
Tooling — Machine output is directly influenced by the type of tools used. It is important to use the tooling expected to be used in normal production. If temporary nonstandard tooling must be used, the machine cycle time and capability criteria must not change.
Machine adjustments — During normal production, machines are sometimes adjusted to attempt to change the mean of the process output. A machine tryout should make as few adjustments as possible. For some machines, a few adjustments are a normal part of the process. However, there is a tendency to want to make many adjustments during a tryout. This should be avoided if at all possible. When unavoidable adjustments and changes are made, they should be recorded in a detailed chronological log. The log should also include information on cycle times, feeds and speeds, tools, coolants, and setup notes. All modifications, even those believed to be of no consequence, should be recorded.
Time — The time required to perform a tryout to obtain the required capability is generally underestimated. In many cases the fine-tuning process requires several months. Sufficient time must be included in the delivery schedule.
Rerun of tryout — Once the machine is installed at the purchaser’s plant, the tryout should be repeated. This will detect any damage incurred in shipping, handling, and installation, as well as establish a baseline for future comparisons. Analysis of the data should include the following steps:
1. Measurement error analysis. The variability of the measurement system should be removed from the data to determine the true machine variability.
2. Run chart. A run chart in the production order should be prepared to evaluate obvious machine problems. It is good practice to number the parts in production order and to save the parts used in the final machine tryout so that they can be reinspected later if necessary.
3. X-bar and R chart. An X-bar and R chart should be prepared to evaluate the stability of the machine. The detailed part-by-part log should be kept to allow the correlation of the X-bar and R data with individual sources of variation.
4. Histograms. Histograms should be prepared to examine the distribution of the data for each of the various sources of variation.